Tugas 2 sofskil (teknik perawatan)
Tugas 2 - PerawatanMesin
Tanggal : 11 juni 2017
Materi : ( Maintenance Costing ) / BiayaPemeliharaan
Khalifah Agung Sedayu – 25414849 – 3IC09
1. To Calculate the mean time to repair (MTTR ) ?
a. Eight Subsytem : a, b, c, d, e, f, g, h form an electronic system.
b. The constants failure rates of these subsystems are :
la = 0.002 ,lb = 0.004 , lc = 0.006 , ld = 0.008 , le = 0.010 , lf = 0.012 , lg = 0.014 , lh = 0.016 failures per hour.
c. The corresponding estimate corrective maintenance time are :
Ta = 2 hour, Tb = 3 hour, Tc = 4 hour, Td = 5 hour, Te = 6 hour, Tf = 7 hour, Tg = 8 hour, Th = 9 hour.
2. Data historical of machine in industry :
a. Hour ( 0 to 200) = up-time
b. Hour ( 200 to 210 ) = down-time
c. Hour ( 210 to 400 ) = up-time
d. Hour ( 400 to 415) = down-time
e. Hour ( 415 to 590 ) = up-time
f. Hour ( 590 to 600 ) = down-time
g. Hour (600 to 750 ) = up-time
To calculate of :
· the mean time to between failure (MTBF ) and mean downtime (MDT) ?
· the annual labor cost of corrective maintenance (CMal) ?
Whereas : SOH = 3500 hour, MTTR = 30 h, LCH = $ 40.
3. Maintenance Cost-Related Data :
Description
|
Manufacture A system
|
Manufacture B system
|
Manufacture C System
|
Expected Life
|
15 years
|
15 years
|
15 years
|
Expected cost of a corrective maintenance action
|
$2000
|
$2500
|
$3500
|
Annual failure rate
|
3 failures per year
|
3.5 failures per year
|
2.5 failures per year
|
Annual interest rate
|
4 %
|
4 %
|
4 %
|
Determine which of the three system will be less costly with present value of corrective maintenance ( Find the value of (PV)?
NB : Using the Formula II.
4. Assume that we have the following time estimates to accomplish an activity :
OT = 85 days
PT = 105 days
MT = 90 days
To Calculate the activity expected duration time ( Ta )?
5. Assume that in maintenance organization we have the following data :
TAH = 2500 hour
BR = 0.2
LR = $25
N = 50
To Calculate the cost per employee (Cem)and The total labor cost ( TLC )?
#Jawaban :
1. 4x10-3 + 0,012 + 0,024 + 0,04 + 0,06 +0,084 + 0,112 + 0,144
0,072
= 0,48
0,072
= 6,67
2. a.MTBF
200 + 190 + 175 + 150
4
= 178,75
MDT
10 + 15 + 10
3
= 11,66
b.= 3500 x 40 x 6,67
178,75
= 933800
178,75
=5224,06
=5224,06
3. MANUFACTURER A SYSTEM
MANUFACTURER B SYSTEM
MANUFACTURER C SYSTEM
4. Calculate the activity expected duration time
5.Calculate the cost per employee (Cem)and The total labor cost ( TLC )
Tidak ada komentar: